ReEdO Watchkeeper · Minutes
MV Example: Drydock planning, week 46
Minutes of meeting · Seawise Marine Services (fictional)
Hull blasting
The yard confirmed that hull blasting can start on 14 November if the class surveyor confirms attendance. Class is booked for 13 November, so the date stands.
Tailshaft survey
The planned duration for the tailshaft survey is five working days: two days for withdrawal and inspection, two for measurements and class attendance, and one for refit.
Actions
Scroll horizontally to see all columns.
| Action | Owner | Due |
|---|---|---|
| Send the bearing clearance report | Omar Haddad (Superintendent) | Before 12 November |
| Confirm class attendance for the tailshaft survey | Liam Turner (Class surveyor) | 13 November |
| Start hull blasting | Sarah Collins (Yard PM) | 14 November |